| All figures stated gross |
Unit |
FY 2011 |
FY 2010 |
Variance |
| Sales |
| Revenue |
US$M |
140.2 |
127.0 |
+10% |
| Diamonds sold |
Carats |
944,405 |
903,861 |
+4% |
| Average price per carat |
US$ |
148 |
141 |
+5% |
| ROM Production |
| Tonnes treated |
Tonnes |
2,323,403 |
2,160,907 |
+8% |
| Grade |
Cpht3 |
36.6 |
38.9 |
-6% |
| Diamonds recovered |
Carats |
851,193 |
841,293 |
+1% |
| Tailings Production |
| Tonnes treated |
Tonnes |
575,605 |
248,380 |
+132% |
| Grade |
Cpht |
7.7 |
34.9 |
-78% |
| Diamonds recovered |
Carats |
44,246 |
86,638 |
-49% |
| Total Production |
| Tonnes treated |
Tonnes |
2,899,008 |
2,409,287 |
+20% |
| Diamonds recovered |
Carats |
895,439 |
927,931 |
-4% |
| Costs |
| On-mine cost per tonne |
ZAR |
164 |
167 |
-2% |
| Total Capex |
US$M |
33.9 |
20.4 |
n/a |
During FY 2011 Cullinan was the major contributor to the Group, accounting for 64% of overall turnover and 80% of carat production. Going forward, the Finsch mine will balance the importance of the Cullinan mine, which was previously the dominant asset in the Group’s portfolio.
The average value per carat (ROM and tailings combined) at Cullinan was US$148 for FY 2011, up 47% in comparison to the US$101 achieved in FY 2010 (being the average for FY 2010 of US$141 after adjusting for the sale of the 507 carat Cullinan Heritage for US$35 million).
In FY 2011, 11 stones from Cullinan each sold for in excess of US$1 million; such stones are regarded as a regular feature of Cullinan’s production profile.
Cullinan performed well in terms of throughput, with total tonnages treated (ROM and tailings) exceeding expectations. ROM grade of 36.6 cpht was approximately 6% lower than the prior year of 38.9 cpht, due to:
- an increase of the bottom cut for slimes discard from 0.8mm to 1.3mm (partially contributing to the increased average value per carat achieved); and
- the far higher than average rainfall experienced in many parts of South Africa, including Cullinan, which results in ore-handling difficulties relating to the clay, mud and moisture content of the ore.
ROM grade at Cullinan is expected to remain under pressure whilst production continues to be from the mature areas of the mine, due to the significant dilution of the ore drawn in these older production zones. However, the grade is forecast to rise to 50 cpht once the new cave is established from FY 2015 onwards as part of the C-Cut development programme on the 830 metre level and undiluted ore is mined and treated.
Although tailings throughput increased significantly to 575,605 tonnes during FY 2011, carats produced from tailings dropped by 49% to 44,246 carats as the high-grade OSP tailings dump was depleted as planned in the preceding year. The Company is now processing the ROM tailings material. The tailings grade of 7.7 cpht achieved for FY 2011 is expected to rise to approximately 10 cpht from FY 2012, once a re-crush system of material larger than 6 mm has been incorporated into the operation.
Despite South African cost pressures, unit costs per tonne at Cullinan decreased by 2% due to increased volumes and other initiatives to mitigate cost pressures. Longer term, once the development plan has significantly progressed in the years to come, further unit cost efficiencies are expected to be driven by initiatives such as a simplified ore-handling system underground and further streamlining of the plant.
Capex at Cullinan increased to US$ 33.9 million for FY 2011, predominantly applied to the underground development work, the continued upgrading of the plant and the new underground fleet equipment.